Asbestos piping at Gateway Arch caused month-long delay

This is an archived article and the information in the article may be outdated. Please look at the time stamp on the story to see when it was last updated.

ST. LOUIS (AP) – Work has resumed on the Gateway Arch’s underground museum after a delay of more than a month caused when a contractor exposed asbestos piping.

The National Park Service says the stoppage will cost about $350,000 and could add weeks to the project’s schedule.

Workers with McCarthy Building Companies cut into asbestos piping and didn’t realize it for a month, exposing people to airborne asbestos.

The St. Louis Post-Dispatch reports the site was shutdown Nov. 3 after the pipe was cut for a second time. Work resumed Dec. 15.

The $380 million project is funded partially by a sales tax in St. Louis County and St. Louis, as well as federal, state, city and private donations.

___
Information from: St. Louis Post-Dispatch, http://www.stltoday.com